Roseville is scaling back plans for a new neighborhood park after construction bids exceeded its $600,000 budget by at least $312,000, raising questions about which amenities the city can afford.
Read more CA joins 12 states seeking to block veterinary supply merger over price concerns
The Roseville City Council voted Nov. 4 to reject all four construction bids for Michael Ziegler Park, a planned 1.7-acre park at Starfield Drive and Nova Place in the Sierra Vista neighborhood.
The city received four bids in April, ranging from $912,409 to more than $1.14 million. Even the lowest bid was more than $312,000 above the amount set aside for construction.
The council also approved revised plans for the park and authorized city staff to seek new construction bids later this year.
The budget challenges come as construction costs continue to rise faster than the development fees used to pay for new neighborhood parks, according to city officials.
“All new neighborhood parks are funded through development fees established as part of the financing plan when a specific plan is approved,” city spokesperson Pamela Allen said.
Michael Ziegler Park is one of 12 neighborhood parks planned for the Sierra Vista Specific Plan area, where development fees were established more than a decade ago.
Allen said those fees are adjusted for inflation, but the increases have not kept pace with rising construction costs.
» Roseville news in your inbox: Get our free Roseville email newsletter here
Why were the construction bids rejected?
The City Council originally approved plans for Michael Ziegler Park on March 18.
The project’s architect had estimated construction costs at $740,000, including all optional improvements. However, the lowest construction bid was nearly 23% higher than that estimate.
Rather than increase the budget to cover the higher bids, the city revised the plans to reduce construction costs.
The revisions included standardizing sidewalks to widths of 4 to 5 feet, reducing planting and irrigation areas, and scaling back certain concrete features.
Could some park features be eliminated?
Could some park features be eliminated?
Despite the changes, Michael Ziegler Park is still planned to include a playground, picnic area, paved walking paths, a multiuse grass area and water-efficient landscaping.
Optional improvements include a half-court basketball area, a shade structure over the picnic area, additional concrete walkways and sod instead of grass grown from seed.
Read more Sacramento could ban horse-drawn carriage rides in Fab 40s during holiday season
The revised plans have lowered the architect’s estimated base construction cost to $525,000.
With all optional improvements, the estimated cost would be $692,517, more than $92,000 over the city’s approved budget.
The city has not announced plans to provide additional funding if the next round of bids exceeds the budget.
Allen said the city hopes opening bids later in the year will result in more competitive prices.
“We’re also using a flexible bidding approach that allows us to evaluate costs for certain amenities separately and prioritize the features residents identified as most important,” she said.
Some amenities could be excluded from initial construction if costs remain too high.
“Once all the parks in Sierra Vista Specific Plan are completed, we’ll review any potential remaining funding and evaluate opportunities to add amenities that couldn’t be included in the original construction budgets,” she said.
When will construction begin?
Roseville plans to open construction bids again in late December, with city staff expected to return to the City Council in January to seek approval of a construction contract.
Construction is expected to begin in early spring 2027, weather permitting.
The city has not provided a projected completion date in its staff report.
The $600,000 construction budget was approved as part of the city’s 2025-26 capital improvement budget, with funding coming from the Neighborhood Park Sierra Vista Fund.
Once the park is completed, annual maintenance costs are expected to total about $27,200, based on the city’s estimate of $16,000 per acre.
Those costs will be paid through the Sierra Vista Community Facilities District No. 2, which funds public services in the area.
Read more CA joins 12 states seeking to block veterinary supply merger over price concerns
According to city staff, the project will not affect Roseville’s general fund.